  • Rehabilitation and upgrade of the boreholes (20 m³/h)
  • Removal of the lamellar clarifier and filter and installation of a new filter
  • Rehabilitation of the treated water pumping station
  • Reinstallation of the disinfection unit
  • Reinstallation of the control panel, the local cabinets, tertiary and the commissioning
  • Reinstallation of the existing generator
  • Rehabilitation, cleaning and disinfection of the elevated tank
  • Reinstallation of the damaged part of the treated water main
  • Densification of the distribution network with laying of 8,000m HDPE OD 90 pipes.

  • Date Started: 2019-06-01
  • Date Completed:Ongoing Project
  • Location: Cameroun
  • Category: Rehabilitation