NSAWAM Drinking Water Supply Project

admin/uploads/blog/d38ee72eaec8acffaf74b775097ad817.jpg

NSAWAM Drinking Water Supply Project

  • Engineering
    • Environmental Impact Studies
    • Structure calculations and detailed design of construction plans
  • Technical Assistance
    • Water audit in Nsawam in order to propose measures to reduce Non-Revenue Water (NRW)
    • Training of GWC staff (operation of the installations and GIS)
  • Construction and installation of the station and fitting equipment
    • Raw water intake
    • Raw water pumping station
    • Dosing and mixing systems
    • Aerator
    • Circular clarifiers
    • Sand filters (Aquazur type)
    • Clear water & backwash pumping stations
    • Connection to the power grid.
    • 12 months of operation assistance during the warranty period equipment
  • Laying of HDPE OD 400 SDR11 pipes: 6,600m from the treatment plant to the existing treated tank
  • Laying of HDPE OD 315 SDR 17 pipes: 12,700m from the existing treated water tank to Pokuase in order to feed 7 new localities.

  • Date Started: 2011-11-01
  • Date Completed:2014-06-01
  • Location: Ghana
  • Category: Construction
  • Tag: