T4-Yaoundé

admin/uploads/blog/156e0d22fd83c64b55210803fa5d29d2.jpg

T4-Yaoundé

  • Installation of a raw water pump (1,458 m³/h at 41.5 m, 250 kW – 6 kV)
  • Installation of a treated water pump (1,389 m³/h at 121m, 650 kW – 6 kV)
  • Installation of the electrical cells and of the remote management system.

  • Date Started: 2013-04-01
  • Date Completed:2014-06-01
  • Location: Cameroon
  • Category: Construction
  • Tag: