C1-Bélabo

admin/uploads/blog/0436e3e860aca6d5cf4f8cea27870a15.jpg

C1-Bélabo

  • Laying of a 7.25 km of HDPE OD 63 and OD 90 pipes
  • Procurement and installation of section valves
  • Installation of 7 washouts
  • Construction of 2 air valve chambers.

  • Date Started: 2016-06-01
  • Date Completed:2016-07-01
  • Location: Cameroon
  • Category: Construction
  • Tag: