ITEN-TAMBACH-NAKURU Water Supply Project (Phase Two)

admin/uploads/blog/efcc4d0a10d19c5c2330496f47257db1.jpg

ITEN-TAMBACH-NAKURU Water Supply Project (Phase Two)

  • Laying of a 32,350 m of HDPE distribution network pipes in Iten
  • Laying of a 19,250 m of HDPE distribution network pipes in Tambach
  • Design and installation of district metered areas (16 main meters)
  • Procurement of 5,000 private meters to be installed by RVWSB
  • Laying of (replacements and extensions; OD 63 to OD 200) a 53,247 metres of HDPE distribution networks in the CBD, Freehold, Pangani, Lake View and Race Track districts of Nakuru city.
  • Laying of 2,000 connections.

  • Date Started: 2016-10-01
  • Date Completed:2018-10-01
  • Location: Kenya
  • Category: Construction
  • Tag: Laying